LTT

Date & Time

Lead Time Timeline Calculator

Build an end-to-end service lead-time network from intake, approval, sourcing, transport, inspection, controlled overlap, and variability, then compare the deterministic path and P90 protection with a promised deadline.

Fully serial duration
Controlled overlap saved
Deterministic path duration
P90 protected duration
P90 promise slack
Longest stage
Parallelized share
Promise status

Lead-time dependency network

A metro-style critical path with one controlled parallel branch

Nodes show operational gates, the approval-to-sourcing branch shows overlap, and the P90 terminus is compared with the promise wall.

A metro-style critical path with one controlled parallel branchUpdates with every input

Stage timing register

Start, finish, dependency, and uncertainty contribution by stage

Audit the end-to-end path rather than relying on one total lead-time number.

Live analysis based on the current calculator inputs
StageDurationStart dayFinish dayDependencyPath roleShare of P50

Network setup

Enter work and waiting stages as separate durations

  1. Measure intake and approval independently.
  2. Use sourcing time from comparable items.
  3. Enter physical transport and receipt inspection.
  4. Allow overlap only where work can truly start early.
  5. Compare the P90 path with the customer promise.

Critical-path logic

Overlap changes dependency timing, not the amount of work

Starting sourcing during approval can shorten the path, but it does not erase either duration.

Variability is applied after the dependency path is calculated so the protection reflects end-to-end observed spread.

Calculation method

Build the dependency path before adding statistical protection

Intake precedes approval. Sourcing may begin during the allowed fraction of approval, then transport and inspection remain sequential. P90 protection is added to the resulting path, not to each stage independently.

Detailed calculation process and general formulas

D_serial=I+A+S+T+RS_start=max(I+A−Ao, I)D₅₀=max(I+A,S_start+S)+T+RD₉₀=D₅₀+1.282σSlack=P−D₉₀

Symbols, meanings, and units

I
intake durationdays
A
approval durationdays
o
allowed approval/sourcing overlapdecimal
σ
end-to-end duration standard deviationdays
P
promised lead timedays

Promise architecture

Separate structural delay from uncertainty protection

The model exposes what is serial, what is deliberately parallel, and what is held as statistical protection.

Serial baseline

All stages with no overlap.

Dependency benefit

Days removed by controlled overlap.

Protected path

P90 end-to-end duration.

Promise margin

Entered promise less P90 duration.

Decision takeaway: Do not call a shorter path safer unless the remaining promise margin still covers end-to-end variability.

Path checks

Validate dependencies before optimizing them

  • Approval may contain hard gates that cannot overlap.
  • Transport variability may be non-normal.
  • Inspection can trigger rework not modeled here.
  • Stage averages must share the same calendar basis.

Timeline evidence

Timestamps that reveal the real critical path

  • Request acceptance time
  • Approval completion
  • Supplier commitment
  • Dispatch and receipt scans
  • Inspection release timestamp

Practical applications

Decisions this calculator is designed to support

Special-order material

A buyer can begin supplier sourcing after partial technical approval.

What the result clarifies: The network quantifies the true benefit of that controlled overlap.

Service onboarding

A provider promises activation after intake, approval, provisioning, transport, and validation.

What the result clarifies: P90 protection shows whether the published promise is robust.

Worked example

Current-input substitution and reconciliation

Model limitations

The P90 approximation assumes an approximately normal end-to-end duration and one observed standard deviation. The model excludes rework loops, correlated stage delays, working-day calendars, capacity queues, and multiple alternative dependency paths.

Lead Time Timeline Calculator FAQ

Why is P90 larger than P50?

It adds a one-sided 90th-percentile protection term to the deterministic path.

Does overlap reduce stage work?

No. It changes start timing only.

Which stage is critical?

The result identifies the longest entered stage, while the network shows the actual dependency path.

What does negative slack mean?

The P90 protected path exceeds the entered promise.