Rooms finished, sign-off pending
Delivered potential exceeds commissioned seats. The arithmetic points to release evidence, not another construction order.
Education
A room can be delivered but not yet usable. This record compares required capacity, delivered room potential, and commissioned seats so the lower of those evidence streams controls completion.
CAPACITY COMMISSIONING
A room can be delivered but not yet usable. This record compares required capacity, delivered room potential, and commissioned seats so the lower of those evidence streams controls completion.
LIVE CAPACITY / SCORE VISUAL
A room can be delivered but not yet usable. This record compares required capacity, delivered room potential, and commissioned seats so the lower of those evidence streams controls completion. The visual updates from the same validated calculation record; it is an interpretation aid, not a policy or compliance ruling.

| Evidence layer | Rooms / seats | Calculated capacity | Controlling value | Release meaning |
|---|
How to use
Completion fundamentals
Calculation method
The page calculates required and delivered potential separately, then takes the minimum of delivered potential, commissioned seats, and required seats. This prevents a physically finished but uncommissioned room from appearing fully complete.
Commissioning
Use the number supported by the release checklist, furniture installation, access review, and local acceptance record. A room count alone cannot prove usable seats.
Scope integrity
If the programme changes from 28 to 30 seats per room, it is a new requirement basis. Recalculate rather than comparing the old completion percentage with a changed target.
Decision boundary
A 100% result means the entered seat quantity has been released against this model. It does not certify teaching quality, safety, accessibility, or long-term maintenance.
Detailed calculation process
The current evidence layers above provide the final reconciliation.
Result interpretation
If delivered potential is higher than commissioned seats, release evidence is the bottleneck. If delivered potential is below the requirement, room delivery is the bottleneck. The effective value controls the percentage in both cases.
Release action
The next action may be commissioning, furniture, room delivery, or requirement clarification. The page makes that difference visible without inventing a cause.
Limits and exclusions
Key terminology
Worked decision cases
Delivered potential exceeds commissioned seats. The arithmetic points to release evidence, not another construction order.
Commissioned capacity cannot exceed what was delivered. The remaining-seat figure stays tied to room delivery.
Authoritative basis
Use completion as a quantity reconciliation. Formal release depends on the responsible authority’s commissioning, safety, and accessibility evidence.
The lower evidence stream controls usable completion.
No; effective delivery is capped at the requirement.
Potential still controls because commissioning cannot create rooms.
No, it only closes the entered seat quantity.
This record rejects that mismatch to keep scope explicit.