Electrical Load Demand Calculator

Apply independent demand factors to lighting, receptacle, and motor groups. Compare connected and diversified kW by group, then calculate continuous-adjusted demand, planned capacity, and the overall demand factor.

Lighting diversified demand (kW)-
Receptacle diversified demand (kW)-
Motor diversified demand (kW)-
Total connected load (kW)-
Diversified demand before allowances (kW)-
Demand after continuous multiplier (kW)-
Capacity including spare allowance (kW)-

Decision view

Group demand dumbbells and capacity stack

Group demand dumbbells and capacity stackConnected and diversified group loads are compared before continuous and spare allowances build the final planning capacity.
Exact scenario comparisonMotor demand factor (%) changes while all other entered assumptions remain constant.
Motor demand factor (%)Lighting diversified demand (kW)Receptacle diversified demand (kW)Motor diversified demand (kW)Total connected load (kW)Diversified demand before allowances (kW)Demand after continuous multiplier (kW)Capacity including spare allowance (kW)

How to use Electrical Load Demand Calculator

  1. Enter connected kW for each load group.
  2. Enter a demand factor for each group.
  3. Set the continuous multiplier and spare percentage.
  4. Compare group dumbbells and the final capacity stack.

Calculator guide

Understanding Electrical Load Demand Calculator

Connected load is the sum of nameplate loads; diversified demand estimates how much of each group operates coincidentally. This calculator keeps those concepts separate before applying continuous-load and spare-capacity allowances.

Groups differ Each demand factor is independent.
Totals reconcile Diversified groups sum to D.
Allowances are sequential Continuous and spare adjustments stay visible.
Capacity exceeds demand Planning margin is intentional.

Calculation method

How the calculation works

Apply separate entered demand factors to three named load groups before adding continuous-load and spare-capacity allowances. Multiply each connected group by its demand factor, sum the diversified groups, apply the continuous multiplier, then add the selected spare-capacity percentage.

Detailed calculation process

Diversify each load group before adding design allowances

The defaults combine 45 kW lighting, 70 kW receptacles, and 120 kW motors with demand factors of 90%, 65%, and 80%.

General formula: D_i = L_i f_i; L_total = sum(L_i); D = sum(D_i); D_c = D m_c; C_plan = D_c(1+s); DF = D/L_total Demand factors apply to named groups before aggregation. The continuous multiplier and spare allowance are separate, sequential capacity adjustments rather than additional connected loads.

What each symbol means

L_i Connected load for group i, measured in kW.
f_i Entered demand factor for group i, unitless.
D_i Diversified demand for group i, measured in kW.
m_c Continuous-load multiplier, unitless.
s Selected spare-capacity fraction, unitless.
C_plan Planned capacity after allowances, measured in kW.

Worked substitution with the default inputs

1. Diversify lighting: D_light = 45 x 0.90 = 40.5 kW Lighting retains 90% of its connected value.
2. Diversify receptacles and motors: D_receptacle = 70 x 0.65 = 45.5 kW; D_motor = 120 x 0.80 = 96.0 kW Each group uses its own entered coincidence assumption.
3. Reconcile connected and diversified totals: L_total = 45+70+120 = 235 kW; D = 40.5+45.5+96 = 182 kW The overall diversified share is 182/235 = 77.447%.
4. Apply the continuous multiplier: D_c = 182 x 1.25 = 227.5 kW This allowance is applied after group diversification.
5. Add spare capacity: C_plan = 227.5 x 1.20 = 273.0 kW The selected 20% spare is measured from continuous-adjusted demand.

The defaults reduce 235 kW connected load to 182 kW diversified demand, then raise the planning basis to 227.5 kW continuous-adjusted and 273.0 kW with spare capacity.

Demand bridge

See diversity and allowances as different operations

A group comparison and capacity stack prevent double counting.

Connected Maximum named group loads.
Diversified Coincident group demand.
Continuous Multiplier applied to diversified total.
Spare Final selected reserve.

Worked situations

Practical examples

  • Receptacle demand falls from 70 to 45.5 kW at 65%.
  • The overall diversified demand factor is 77.447%.
  • Allowances raise the planning capacity to 273 kW.

Better inputs

Useful tips

  • Apply demand factors to the correct occupancy and equipment group.
  • Keep continuous-load rules separate from diversity.
  • Document whether spare is applied before or after other allowances.

Before relying on the result

Limitations and common mistakes

  • Applicable factors and multipliers depend on jurisdiction and system purpose.
  • Motor starting, phase balance, harmonics, emergency loads, and coincidence studies are excluded.
  • The result is not a code-compliant feeder or transformer selection by itself.

Reference

Key terms

Connected load
Sum of installed or nameplate load.
Diversified demand
Modeled coincident operating load.
Spare capacity
Selected planning allowance above adjusted demand.

Important note

Calculated from the entered values using the displayed engineering relationship. Confirm design values, load cases, safety factors, standards, and field conditions with a qualified professional.

Frequently asked questions

Why not multiply the total by one demand factor?

Different load groups can have different operating patterns and entered factors.

Is spare capacity a demand factor?

No. It is an allowance added after the modeled demand.

Can planned capacity exceed connected load?

Yes, depending on continuous and spare multipliers.

Does this size conductors?

No. Electrical code, voltage, current, protection, and installation conditions remain separate.